In the August 1997 issue of the Items of Engineering
Interest, RUS summarized information that borrowers need to include with their requests
for RUS approval to use steel distribution poles. These guidelines have been slightly
revised and are provided below.
In order to assist the RUS staff in considering requests to use steel
distribution poles, borrowers should adequately address in writing items 1 through 8
below. Currently, approval to use steel distribution poles is only being granted on a
case-by-case trial basis to gain experience.
Information to include in requests to use steel distribution poles:
- Because approval is only being considered for site specific projects, define the project
and where the steel poles will be installed.
- State the maximum number of steel poles to be used.
- Furnish reasons for using steel poles. If favorable cost is the main reason, then
include an engineering economic analysis of the cost of using steel poles compared with
standard RUS construction with wood poles. This analysis should include the additional
cost (if any) for equipment and material needed to compare both structure types as
equivalent in mechanical strength, raptor protection, and quality of service such as
blinking lights due to lightning flashovers.
- Provide a description of the proposed steel poles and the method(s) of corrosion
protection to be utilized when manufactured, when placed in service and for future
maintenance.
- RUS regulations require that all assembly units must be built according to RUS
construction standards. If nonstandard assembly top construction is being proposed, then
furnish sufficient dimensioned drawings and other technical information for RUS
evaluation of the design.
- Except for various miscellaneous material items, RUS regulations require that borrowers
use materials that RUS has accepted or technically accepted. A compilation of accepted
materials may be found in Informational Publication 202-1, "List of Materials
Acceptable for Use on Systems of RUS Electrification Borrowers." Contact the Chair,
Technical Standards Committee "A" (Electric) for information on technically
accepted items. If the proposed design uses materials that do not fall into the any of the
acceptance categories above, then furnish RUS sufficient information, data and test
results of all such materials for evaluation and approval determinations.
- Indicate that the steel poles to be used have been selected based on engineering
calculations considering the expected duty and conditions to which they will be exposed.
(See also "Wood Equivalent Steel and Concrete Poles" in this issue.)
- Provide a statement regarding the anticipated impact that the pole-top assembly design
of the steel pole may have on the possible electrocution of raptors. Also state the
mitigation measures that will be incorporated in the design to minimize such
possibilities.
The following design information should also be considered but does not
have to be submitted to RUS:
RUS strongly advocates a minimum lightning impulse withstand strength
(often incorrectly and simply referred to as a BIL level) of 300 kV for distribution
pole top assemblies. A minimum of 300 kV withstand needs to be maintained at
dead-end assemblies. Withstand strengths of less than 300 kV will usually
facilitate flashovers of lightning strikes to or proximate to distribution lines. A
recloser operation, which will cause lights to flicker, is usually required to clear the
resulting arc. Thus, a minimum of 300 kV withstand is required to maintain a
reasonable quality of service. Standard RUS pole type assemblies, with wood poles, have a
minimum withstand strength of 350 to 400 kV. If the steel pole design has a withstand
strength of less than 300 kV, borrowers should consider what additional measures,
such as the installation of surge arresters, might be used to minimize flashovers, or,
what impact a design with a withstand strength of less than 300 kV might have on the
quality of service.
A steel pole may be used as a grounding conductor if the pole meets the
sufficient conductivity and low impedance requirements of the NESC and RUS specifications.
However, a directly embedded steel pole is not recognized in the NESC as a grounding
electrode. Thus, the NESC and RUS requires that separate driven ground rods or grounding
electrodes be used for all equipment, surge arresters and other required system grounds,
including grounding the poles themselves, if needed to provide adequate grounding. (See
NESC Rule 215.C.1.)
Borrowers should use stainless steel or galvanized steel ground rods
and non-copper ground wire in the soil on steel pole lines to mitigate the corrosive
effects of buried dissimilar metals in close proximity.
The design of unguyed angle and dead-end steel pole structures should
consider pole deflection and the possible need for greater embedment depths.
For NESC Grade C construction, there should not be a direct
substitution of wood poles with steel poles of the same designation. Engineers should
calculate the design load and select the standard class steel pole based on these
calculations. Extreme ice conditions and appropriate high winds should be considered in
the design loads. (See also "Wood Equivalent Steel and Concrete Poles" in this
issue.) For steel poles on distribution lines, RUS advocates the use of NESC Grade B
overload factors for angle and deadend (guyed or unguyed) structures.
The information requested above is needed to insure a safe, reliable,
and economical distribution line when using steel poles. Considerations such as these plus
many other design considerations are incorporated into all RUS standard designs for
overhead distribution lines. RUS is developing a guide specification for steel
distribution poles which, when finalized, borrowers could use to purchase and use steel
distribution poles without further RUS approval.
If you would like further information or have any questions, please
call Harvey Bowles, Chief, Distribution Branch, at (202) 720-5082, or Bob Lash,
Chief, Transmission, at (202) 720-0486. |